Mid-day Briefing: Data Centers

Monday, June 15, 2026 · 6:49 PM EDT

Key developments

ROCHESTER BUSINESS JOURNAL

New York advances hyperscale data center moratorium

New York lawmakers approved a one-year moratorium on permits for new data centers with peak electricity demand of 20 megawatts or more, pending Gov. Kathy Hochul’s signature. The pause would allow state review of impacts on energy demand, utility rates, water resources and environmental conditions. The measure directly affects debate around Stream Data Centers’ proposed $19.5 billion, 2.2 million-square-foot STAMP campus in Genesee County, which critics say could require about 500 megawatts of power.

Why it matters

If signed, New York would become the first state to temporarily halt new hyperscale data center development while studying grid, water and ratepayer impacts.

Sources & driving stories

ROCHESTER BUSINESS JOURNAL · Andrea Deckert

Rochester Business Journal coverage
WIRED

Federal data center oversight law may lapse

WIRED reported that the Federal Data Center Enhancement Act, passed in 2023, is set to expire in September without an evident replacement from Congress or the Trump administration. The law requires federal agencies to consider and report on data center energy use, water use, sustainability, efficiency and contractor-site performance. The Register separately noted the law also covers uptime, power-failure protection, physical security and natural-disaster resilience standards.

Why it matters

A lapse would reduce federal visibility into data center resource use, cybersecurity and procurement discipline just as federal AI infrastructure demand is rising.

Sources & driving stories

THE REGISTER · Dan Robinson

The Register coverage
TENNESSEE LOOKOUT

Local data center moratoria spread in Tennessee

McMinnville and Coffee County, Tennessee, unanimously passed data center moratoria on June 9 after resident opposition, according to Tennessee Lookout reporting by Cassandra Stephenson. Nashville’s council also advanced a moratorium bill on first reading June 9, with a separate restrictions bill set for Planning Commission consideration June 25. Officials cited electrical grid capacity, water and stormwater impacts, environmental and public health concerns, noise and community fit; a proposed Hixson Data Center would be a 96,064-square-foot, 25-megawatt facility using natural gas and diesel generators.

Why it matters

The Tennessee actions show local governments moving faster than state regulators to pause or condition data center siting amid power, water and neighborhood concerns.

Sources & driving stories

TENNESSEE LOOKOUT · Cassandra Stephenson

Tennessee Lookout coverage

Worth noting

WORTH NOTING

Maryland shifts grid upgrade costs

The Daily Record reported that Maryland’s new Utility RELIEF Act requires data centers and other large-load customers to register with the Public Service Commission and pay for transmission and distribution upgrades needed for grid connection.

WORTH NOTING

Virginia tax exemption fight escalates

WAVY reported that state Sens. Louise Lucas and Mamie Locke used a June 14 Hampton listening-tour event to advocate removing data center tax exemptions in Virginia’s next state budget, due June 30.

WORTH NOTING

Floating data center prototype tested

Forbes reported that Panthalassa is testing its Ocean-2 wave-powered floating data center node off Washington state and is targeting commercial units in 2027 after raising $140 million in May.

Still unclear

OPEN QUESTION

Will Hochul sign New York’s moratorium?

The governor’s decision will determine whether New York becomes a test case for statewide hyperscale permitting pauses and could affect Stream’s $19.5 billion Genesee County project.

OPEN QUESTION

Who pays for grid capacity?

Maryland, Tennessee, Kentucky, Wisconsin and Texas signals all point to unresolved disputes over whether data centers, utilities or ordinary ratepayers should bear new infrastructure and reliability costs.