Digital Realty's Data-Center Expansion
Coverage from AOL, Fool, and others

Digital Realty Trust develops and leases data centers for cloud, AI, and hyperscale computing, combining real-estate expansion with substantial power and capital requirements.
Its buildout includes a planned campus near De Soto, Kansas, where 1,440 acres and an initial 600 megawatts of utility power support a project that could grow to 2 gigawatts, alongside development in markets such as Indianapolis and Ankara. Leasing pipelines and financing strategies help fund that growth, while power procurement, permitting, equipment availability, community concerns, and resource use shape where and how quickly facilities can be built.
If you read one thing
It gives the broadest overview of Digital Realty’s demand, construction pipeline, and execution constraints.
Latest development
The Q3 call adds a material update on AI-driven bookings and new private capital for hyperscale expansion.
The local angle
It makes the Kansas City buildout concrete with the land acquisition and staged power and capacity plans.
Demand is converting into strong leasing commitments
AI-related activity is contributing to Digital Realty's bookings, while record quarterly leasing and interconnection activity and a substantial backlog show demand translating into customer commitments.
A large, expanding construction pipeline
Digital Realty has about 1.5 GW under construction at an expected cost of $22 billion, with 63% pre-leased. The pipeline has grown from the 1.4 GW previously reported, while its scale leaves delivery dependent on substantial capital and execution.
11.5% percent
expected stabilized yield
“Digital Realty’s development pipeline includes 1.4 gigawatts under construction at a total cost of $20 billion. The pipeline is 63% pre-leased and has an expected stabilized yield of 11.5%.”
63%
Share of development pipeline pre-leased
“The development pipeline remains 63% pre-leased at an 11.6% average expected stabilized yield.”
$424 million USD
annualized gross bookings
“Revenue reached $2.625 billion, up 16.4% year over year, while annualized gross bookings rose 23% to $424 million and net interconnections reached a record 9,700.”
110 megawatts MW
capacity leased year to date
“Iron Mountain leased 110 megawatts year to date through July, including a 51-megawatt Mumbai lease with a major hyperscaler on a 10-year contract and a 25-megawatt lease that fully leased London 3.”
16.4% percent
year-over-year revenue growth
“Revenue reached $2.625 billion, up 16.4% year over year, while annualized gross bookings rose 23% to $424 million and net interconnections reached a record 9,700.”
Record leasing and private capital support a larger Digital Realty buildout
Digital Realty reported record quarterly leasing, with its construction pipeline growing to 1.5 gigawatts and 63% pre-leased. More than $1.4 billion in cornerstone commitments for a new private-capital strategy adds a funding source for stabilized North American hyperscale facilities.
Previously
Data center investment is growing alongside reported AI, cloud, and hyperscaler demand. Digital Realty is the clearest recurring actor, with a large construction pipeline, a planned Kansas City campus, and a new Nairobi facility. Prologis, Equinix, and Iron Mountain also report expansion or leasing activity. Power availability, permitting, equipment supply, construction costs, and financing remain practical constraints on how quickly planned capacity can be delivered.
Digital Realty’s record Q3 leasing bookings and larger, 63%-pre-leased construction pipeline strengthen evidence that demand is translating into committed customer activity. Capital availability and local concerns are also more prominent as execution constraints.