Quantica Broadview Campus Faces Local Review
Coverage from Montana Free Press, Q2 News (KTVQ), and others
Articles
4
Active Days
31
The Topic

Quantica Infrastructure is planning a 5,000-acre data center campus near Broadview, Montana, with a first building targeted for 2029. The company has sought grid capacity of up to 7,235 megawatts while evaluating renewable power, battery storage, and 1,785 megawatts of potential gas generation. The proposal remains early-stage and faces air-permitting requirements, environmental concerns, and an effort by nearby residents to require voter approval.
First Article: 05/20/26
Latest Article: 06/19/26
Summary
- Quantica is planning a 5,000-acre, 12-to-16-building campus near Broadview, north of Billings.
- The company requested up to 7,235 megawatts of interconnection capacity after previously describing demand of about 1,000 megawatts.
- Potential power sources include renewables, battery storage, on-site gas generation, and other firming resources.
- Montana DEQ indicated the proposed gas facilities could require a Major NSR-PSD air permit, public review, and likely an environmental impact statement.
- Nearby residents are pursuing a ballot initiative that would require a two-thirds vote to approve data centers.
- Critics have raised concerns about electricity rates, groundwater, cooling, emissions, wastewater, noise, traffic, and transparency.
- A union memorandum supports workforce training and project stability, but construction and operating approvals have not been secured.
History
The main update is that Quantica has now tied the Broadview campus to a clearer timeline, with a first building targeted for 2029, while its power strategy has broadened and become more explicit. The regulatory and local-approval picture is also more concrete, with air-permitting scrutiny and a resident ballot effort now standing out as the key obstacles.
The biggest update is that Quantica’s power plan has become more explicit and more contentious: it is now tied to a possible 1,785-megawatt gas-fired component and state regulators are signaling major air-review requirements. At the same time, the story adds a labor agreement and clearer local push for a public vote, sharpening the approval fight.