OpenAI’s Ohio Data Center Campus

Coverage from Yahoo, WLWT, and others

OpenAI’s Ohio Data Center Campus topic image

The planned campus at the PORTS-Pike Technology Campus in Pike County, Ohio, is intended to provide large-scale computing capacity for OpenAI under a long-term lease.

SB Energy, a SoftBank subsidiary, is expected to build, own, and operate the site, while Nvidia is tied to reported financing support, chip supply, and investment in SB Energy. The project’s scale also depends on power generation and regional grid infrastructure, with AEP Ohio among the partners mentioned. Reported capacity, financing, construction, and employment figures describe plans and projections, not necessarily completed commitments.

Key Articles4 of 41 articles

If you read one thing

Reuters lays out the core project commitments alongside the planned generation, grid investment, and phased capacity.

Reuters / Anhata Rooprai and Aditya Soni

Best explainer

This local report adds context on the campus’s phased costs, permitting, environmental review, and community commitments.

Cincinnati Enquirer

The evidence

SB Energy’s IPO disclosures provide distinct evidence about its pre-operational losses and dependence on OpenAI and partner financing.

CNBC

The local angle

It reports how the proposed campus is already affecting local housing concerns and community commitments.

Yahoo
Key Issues

A defined project, still awaiting phased delivery

OpenAI is the planned long-term tenant and SB Energy the developer and operator of a multi-gigawatt campus. Reported lease terms and phased capacity schedules describe a planned buildout, not an operational campus.

Stable

Drawn from 4 articles

Execution depends on concentrated partner financing

Nvidia’s reported campus guarantee is capped at $105 billion and phases in as buildings are completed; reporting says no guarantee payments had been made as of October 25. SB Energy’s filing describes a pre-operational data-center business reliant on outside financing and substantially dependent on OpenAI, keeping execution closely tied to key partners.

Stable

Drawn from 3 articles

Power and grid buildout are prerequisites

The planned compute capacity depends on substantial new generation and regional grid investment, including transmission upgrades. Early phases are expected to use existing AEP infrastructure, but these plans remain development requirements rather than evidence of completed operating capacity.

Stable

Drawn from 4 articles

Key Numbers

$105 billion USD

maximum guarantee exposure for the campus

declines over the lease terms as OpenAI makes payments

“As buildings come online, Nvidia’s guarantee exposure will build. Each guarantee takes effect only after its associated building is completed and ready for service. The first is expected in fiscal 2029. Exposure will reach a maximum of $105 billion and then decline over the lease terms as OpenAI makes payments. Nvidia said it had made no guarantee payments as of Oct. 25.”

Data Center Knowledge

20-year years

term of OpenAI leases at the campus

subject to limited exceptions

“The largest guarantee supports SB Energy’s PORTS-Pike Technology Campus in Ohio. Nvidia is providing credit support for approximately 4.25 GW across nine buildings. The campus will host Nvidia infrastructure under 20-year leases to OpenAI, subject to limited exceptions.”

Data Center Knowledge

approximately 4.25 GW

capacity supported at PORTS-Pike

across nine buildings

“The largest guarantee supports SB Energy’s PORTS-Pike Technology Campus in Ohio. Nvidia is providing credit support for approximately 4.25 GW across nine buildings. The campus will host Nvidia infrastructure under 20-year leases to OpenAI, subject to limited exceptions.”

Data Center Knowledge

nine buildings

buildings at PORTS-Pike

“The largest guarantee supports SB Energy’s PORTS-Pike Technology Campus in Ohio. Nvidia is providing credit support for approximately 4.25 GW across nine buildings. The campus will host Nvidia infrastructure under 20-year leases to OpenAI, subject to limited exceptions.”

Data Center Knowledge

up to $118 billion USD

financial guarantees tied to AI infrastructure projects

maximum gross guarantee amount

“Nvidia reported $107.6 billion in data center revenue Tuesday, up 110% from a year earlier, and disclosed up to $118 billion in financial guarantees tied to AI infrastructure projects. The guarantees put Nvidia on the hook for financing arrangements designed to help customers secure the land, power, and facilities needed to deploy its systems.”

Data Center Knowledge

Looking Back
163 Day Timeline
Jun 10Jul 8Aug 5Sep 16Oct 14Nov 11
The Story So Far
No material change

New reporting reiterates the previously described phased Nvidia guarantee and adds no material change to the project’s status.

Previously

OpenAI plans to lease the PORTS-Pike Technology Campus in Pike County, Ohio, from developer and operator SB Energy under a 20-year agreement. The announced plan targets about eight gigawatts of computing capacity, beginning with 800 megawatts in 2028 and building out through 2032. Nvidia is the exclusive chip supplier and has committed financial support, while SB Energy, SoftBank, and AEP Ohio are planning substantial generation and grid investment. Site remediation, permits, financing, and power infrastructure remain important execution requirements.

All Articles41 articles
Interesting2 articles · CI Score 59.6–68.51
Yahoo
OpenAI, Nvidia, and SB Energy are planning an 8GW AI data center and natural gas plant near Piketon, Ohio, for 2028 operation.
8/26/2026 • Community & Local Opposition • Community Benefits & Jobs
Yahoo
SB Energy, OpenAI and Nvidia are developing an 8GW AI datacenter in Piketon, Ohio, targeted to open in 2028 amid concerns about power, pollution, water, housing, and radioactive-site cleanup.
8/26/2026 • Community & Local Opposition • Community Benefits & Jobs
Additional39 articles · CI Score below 59.6
WLWT / Kurt Knue
Nvidia announced financing and chip supply for OpenAI's planned eight-gigawatt PORTS-Pike Technology Campus in Piketon, Ohio, targeted for completion by 2032.
8/26/2026 • Power Procurement & Grid • Load Growth & Capacity
AOL / Aj Tiarsmith
On July 27, 2026, Jim Cramer warned that Nvidia's potential financing support for OpenAI's Ohio AI campus could expose Nvidia to major counterparty losses.
9/7/2026 • Project Finance & Incentives • Project Capital Structure
Aol / Motley Fool
In its fiscal third quarter of 2027, Nvidia outlined a $105 billion lease guarantee for OpenAI's Ohio AI data center campus, scheduled to begin across nine buildings in fiscal 2029.
11/19/2026 • Market Demand & Investment
CNBC / Zev Fima
Nvidia reportedly discussed financing support for OpenAI to lease a proposed 10-gigawatt data center in southern Ohio, developed by SB Energy.
7/27/2026 • Market Demand & Investment
Yahoo / Talha Qureshi
OpenAI seeks to lease a 10-gigawatt Ohio data center campus developed by SB Energy, with an initial phase expected to start operations in 2028.
6/22/2026 • Market Demand & Investment
Yahoo
OpenAI is reportedly discussing a 10-gigawatt Ohio federal-land data center campus lease, with SB Energy development and anticipated Nvidia hardware and financial guarantees.
6/10/2026 • Market Demand & Investment
The Columbus Dispatch
OpenAI is reportedly negotiating a 20-year lease for a proposed 10-gigawatt data center campus on federal land in southern Ohio, with Nvidia expected to supply hardware and guarantee financing.
6/10/2026 • Market Demand & Investment
Reuters / Anhata Rooprai and Aditya Soni
Nvidia agreed to guarantee up to $105 billion for OpenAI's planned Ohio data center lease in Pike County, with initial capacity expected in 2028.
8/17/2026 • Project Finance & Incentives • Project Capital Structure
OpenAI
OpenAI and SB Energy agreed to develop an 8-gigawatt AI data center campus through 2032 at the PORTS-Pike Technology Campus in Ohio.
8/17/2026 • Infrastructure & Site Development • Industrial Parks & Campuses
Data Center Dynamics / Sebastian Moss
Nvidia will phase financial support for SB Energy's Ports-Pike data center in Ohio from 2028 through 2030 to secure AI capacity and power.
8/17/2026 • Project Finance & Incentives • Project Capital Structure
AOL / Anhata Rooprai
Nvidia agreed Monday to guarantee up to $105 billion in lease payments for OpenAI's AI data center campus being developed by SB Energy in Pike County, Ohio.
8/17/2026 • Project Finance & Incentives • Project Capital Structure
Forbes / Ty Roush
Nvidia and OpenAI discuss a proposed 10-gigawatt Ohio data center near Columbus, with SBEnergy developing the site and first-phase power targeted for 2028.
7/27/2026 • Power Procurement & Grid
Cincinnati Enquirer
OpenAI announced on August 17 plans to lease an 8-gigawatt Nvidia AI data center at the PORTS-Pike Technology Campus in Southern Ohio.
8/25/2026 • Infrastructure & Site Development • Construction & Buildout
NBC4 / Katie Millard
OpenAI, S.B. Energy, NVIDIA, and the U.S. Department of Energy announced plans for an 8-gigawatt AI data center at a former nuclear enrichment site in Pike County, Ohio.
8/18/2026 • Market Demand & Investment • Tenant Expansion & Leasing
Data Center Knowledge / Shane Snider
On November 18, 2026, Nvidia disclosed guarantees supporting SB Energy's 4.25 GW PORTS-Pike AI campus in Ohio, with OpenAI expected to lease its facilities.
11/18/2026 • Project Finance & Incentives
CNBC
SB Energy filed an IPO prospectus with the U.S. Securities and Exchange Commission on Tuesday, disclosing financing dependence and risks surrounding planned Ohio data center construction.
9/1/2026 • Project Finance & Incentives • Project Capital Structure
The New York Times / Maureen Farrell and Cade Metz
OpenAI, via SoftBank-led development, negotiates a $500 billion Ohio data center lease with Nvidia-backed financial support and 10 gigawatts of power involvement.
7/28/2026 • Project Finance & Incentives
New York Post / Marc Vartabedian
Nvidia is reportedly in talks with OpenAI and SB Energy to provide a 250 billion financing package for a 10 gigawatt Ohio data center, tied to tariff-funded gas generation.
7/27/2026 • Project Finance & Incentives
Data Center Dynamics / Sebastian Moss
Nvidia is negotiating a $250 billion financing backstop for an OpenAI data center planned for southern Ohio, supported by SoftBank SB Energy's 10GW natural-gas power buildout.
7/27/2026 • Project Finance & Incentives
CNBC / Kate Rooney
OpenAI is negotiating an up to 250 billion Nvidia credit backstop to finance lease and construction debt for a 10 gigawatt AI data center campus in Pike County, Ohio.
7/27/2026 • Project Finance & Incentives
The Columbus Dispatch
Nvidia financing guarantee talks are reported to support OpenAI leasing a 10-gigawatt Pike County, Ohio data center as Howard Lutnick allocates government-controlled power access.
7/27/2026 • Project Finance & Incentives
The Columbus Dispatch / Dean Narciso
OpenAI, SB Energy, and NVIDIA plan a six-year, eight-gigawatt AI data center buildout at the former Portsmouth Gaseous Diffusion Plant in Pike County, Ohio, beginning with 800 megawatts in 2028.
8/17/2026 • Infrastructure & Site Development • Construction & Buildout
CNBC / Samantha Subin
Nvidia, OpenAI, SB Energy, and SoftBank are developing a phased 10-gigawatt AI data center and power project in Pike City, Ohio, beginning in 2028.
8/17/2026 • Project Finance & Incentives • Debt & Equity Financing
TechCrunch
Nvidia announced Monday a $1.5 billion investment and major financing commitment for OpenAI's Ports-Pike data center and associated power development near Cincinnati, Ohio.
8/17/2026 • Project Finance & Incentives • Debt & Equity Financing
TechRepublic / David Curry
Nvidia plans a $1.5 billion investment in SB Energy to support construction of an Ohio data center for OpenAI.
8/18/2026 • Market Demand & Investment • AI Infrastructure Demand
NBC4 WCMH / Katie Millard
The DOE and SB Energy are developing a proposed 10-gigawatt AI data center at the former PORTS site in Pike County, Ohio, with Nvidia and OpenAI reportedly considering a lease.
7/30/2026 • Market Demand & Investment • AI Infrastructure Demand
Reuters / Disha Mishra
Nvidia is discussing up to $3 billion in investment and broader credit support for SB Energy's planned OpenAI data center campus in Ohio.
8/15/2026 • Project Finance & Incentives • Debt & Equity Financing
Yahoo / Vlad Schepkov
Nvidia agreed to provide up to $105 billion in credit support for SB Energy's OpenAI data center at Ohio's PORTS-Pike Technology Campus, with initial operations planned for 2028.
8/17/2026 • Project Finance & Incentives • Project Capital Structure
New York Post / Thomas Barrabi
Nvidia and OpenAI announced a financing and leasing arrangement for an eight-gigawatt AI data center in Pike County, Ohio, with initial capacity planned for 2028.
8/17/2026 • Project Finance & Incentives • Project Capital Structure
The New York Times
Nvidia agreed Monday to finance up to $105 billion of an Ohio data center that OpenAI will lease as completed capacity becomes available from 2028.
8/17/2026 • Project Finance & Incentives • Project Capital Structure
CNBC
Nvidia is reportedly discussing up to $3 billion for SB Energy and credit support for an OpenAI data center campus planned in Ohio.
8/15/2026 • Project Finance & Incentives • Project Capital Structure
Reuters
Nvidia discussed providing $250 billion in financing guarantees for OpenAI to lease and finance a 10-gigawatt data center in southern Ohio, with 2028 phase completion.
7/26/2026 • Project Finance & Incentives
International Brotherhood of Boilermakers
SB Energy and SoftBank Group announced plans for the PORTS Technology Campus, a 10-gigawatt AI data center and gas-generation complex, in Piketon, Ohio.
7/28/2026 • Infrastructure & Site Development • Construction & Buildout
The Wall Street Journal
NVIDIA reportedly discusses a $250 billion backstop for OpenAI to lease a 10-gigawatt data center project in southern Ohio being developed by SoftBank energy.
7/26/2026 • Project Finance & Incentives
Reuters / Mrinmay Dey
Nvidia is expected to reduce its initial financial backstop for OpenAI's proposed 10-gigawatt Ohio data center project before a possible agreement around August 14.
8/14/2026 • Project Finance & Incentives • Debt & Equity Financing
CNBC / Ari Levy
Nvidia announced Monday that Nvidia will support up to $105 billion of OpenAI's planned four-gigawatt data center development at the PORTS-Pike Technology Campus in Pike County, Ohio.
8/18/2026 • Project Finance & Incentives • Project Capital Structure
Aol / Jared Blikre
After Jensen Huang's Thursday departure, Nvidia's guarantee of up to $105 billion for OpenAI's Ohio data-center leases drew scrutiny over AI buildout financing risks.
11/12/2026 • Market Demand & Investment
CNBC / Alexa LoMonaco
Nvidia discussed a $250 billion backstop in financing talks for OpenAI’s planned 10-gigawatt AI data center campus in Ohio as AI infrastructure investment risk concerns emerged.
7/27/2026 • Project Finance & Incentives
AOL / Rich Duprey
Nvidia reportedly discussed up to $600 billion in unconfirmed financing support for OpenAI infrastructure and GPU purchases, including a planned Ohio data center.
7/27/2026 • Project Finance & Incentives