Executive Summary

ACME Solar commissioned new battery storage in Rajasthan and signed more dispatchable power deals, expanding its clean power portfolio and grid support

  • ACME Solar commissioned 143MW/481.48MWh of BESS in Rajasthan, its first battery storage projects
  • The storage assets are part of a planned 585MW/2,011.24MWh buildout across multiple SPV subsidiaries
  • The batteries connect to India's Inter-State Transmission System and will first run on merchant arbitrage
  • ACME plans to pair the storage with future Firm Dispatchable Renewable Energy projects under long-term PPAs
  • A separate Rajasthan BESS phase at Jaimalsar, Bikaner covers 250MW/1103.392MWh and has a 60MW phase I
  • That Jaimalsar phase I has a commercial operation date of March 25, 2026
  • ACME also signed 3.1GWh of BESS supply agreements with Trina Storage and Narada Power in July 2025

Quick Facts

  • What: Commissioned BESS and signed dispatchable power agreements
  • Where: Rajasthan and other Indian states
  • Why: To support peak power delivery and future firm renewable supply
  • Who: ACME Solar Holdings and its subsidiaries
  • When: In 2025 with phase I COD in March 2026

Coverage Timeline: 386 Days

1Mar 4 '251Mar 23 '262Mar 24 '26

Featured Article

Energy-Storage.News / Andy Colthorpe 03-23-2026
ACME Solar commissioned 143MW/481.48MWh of Rajasthan BESS systems in 2025, connecting to India’s Inter-State Transmission System for merchant arbitrage and future firm dispatchable renewables under PPAs.

Additional Articles

⭐⭐⭐

Udaipur Kiran / Bhupendra Singh Chundawat 03-24-2026
ACME Solar Holdings and ACME Surya Power commissioned the BESS phase I in Jaimalsar, Bikaner, Rajasthan, with March 25, 2026 COD.
pv magazine India / Uma Gupta 03-24-2026
ACME Solar Holdings commissioned additional 155 MW BESS in Rajasthan to expand merchant peak-shifting capacity connected to the inter-state transmission system.

⭐️⭐️

Propnewstime 03-04-2025
ACME Solar Holdings subsidiary signed two 25-year PPAs with SJVN for 450 MW dispatchable solar in Rajasthan under FDRE through tariff-based competitive bidding.