Liddell Battery Nears Mid-Year Start

Coverage from SolarQuarter, Energy-Storage.News, and others

Articles

3

Latest Article

03/23

Active Days

2

Executive Summary

Australia's 500MW Liddell battery nears commissioning to store solar power, back up the grid, and replace retired coal capacity.

  • 500MW/1000MWh Liddell Battery has completed construction and is now being commissioned
  • First 250MW is undergoing staged testing before full commercial operations
  • Full operations are expected by mid-2026 or June 2026
  • Project repurposes the former Liddell coal plant site in New South Wales
  • Battery is designed to store excess renewable energy and dispatch it at peak demand
  • Federal support includes AU$35 million from ARENA and NSW backing through an LTESA
  • Construction peak created more than 600 jobs and used strong local procurement

Quick Facts

  • What: Commissioning a 500MW 1000MWh grid battery
  • Where: Former Liddell Power Station site in New South Wales
  • Why: To firm renewable power and replace retired coal capacity
  • Who: AGL and Australian and NSW governments
  • When: Commissioning underway with operations due mid-2026

Coverage Timeline: 2 Days

1Mar 22 '262Mar 23 '26

Featured Article

2NM / Cameron Smith 03-22-2026
NSW commissioning of the Liddell Battery near Muswellbrook, Australia, is underway ahead of a mid-year start after construction completion and federal and state funding support.

Additional Articles

⭐⭐⭐

SolarQuarter 03-23-2026
Australian and New South Wales governments back commissioning of the 500MW/1000MWh Liddell Battery in mid-year plans to firm renewables in the National Electricity Market.
Energy-Storage.News / George Heynes 03-23-2026
AGL began commissioning a 500MW/1,000MWh Liddell battery energy storage system in New South Wales, with full operations planned for June 2026.