Liddell Battery Nears Mid-Year Start
Coverage from SolarQuarter, Energy-Storage.News, and others
Articles
3
Latest Article
03/23
Active Days
2
Executive Summary
Australia's 500MW Liddell battery nears commissioning to store solar power, back up the grid, and replace retired coal capacity.
- 500MW/1000MWh Liddell Battery has completed construction and is now being commissioned
- First 250MW is undergoing staged testing before full commercial operations
- Full operations are expected by mid-2026 or June 2026
- Project repurposes the former Liddell coal plant site in New South Wales
- Battery is designed to store excess renewable energy and dispatch it at peak demand
- Federal support includes AU$35 million from ARENA and NSW backing through an LTESA
- Construction peak created more than 600 jobs and used strong local procurement
Quick Facts
- What: Commissioning a 500MW 1000MWh grid battery
- Where: Former Liddell Power Station site in New South Wales
- Why: To firm renewable power and replace retired coal capacity
- Who: AGL and Australian and NSW governments
- When: Commissioning underway with operations due mid-2026