SunZia Wind and Transmission Project
Coverage from Vox, Grist, and others

SunZia combines a New Mexico wind project of roughly 916 turbines with a 550-mile high-voltage direct-current line that carries electricity through Arizona toward California and the wider western grid.
Pattern Energy developed the linked generation and transmission infrastructure to connect a large wind resource with distant electricity markets. The project’s route, permitting, and operation have involved questions about wildlife and habitat, culturally significant places, and the infrastructure needed to move renewable power across regions.
SunZia’s transition into service is now more definite: reports say deliveries began in 2026 and the project was fully operating by June. The 3-gigawatt transfer capacity and SRP’s ramp-up target through summer 2027 add operational detail.