Data Center Site Constraints Are Coming Into Sharper Focus
Six regional grid operators have proposed new terms for connecting large electricity users, including data centers. Legal analysis published yesterday shows how those terms could affect upgrade costs, financial commitments and the ability to draw power.
Separate reporting clarifies California’s environmental-review requirements and the spread of state water measures. Together, they make site comparisons more concrete—not because the rules changed yesterday, but because their potential consequences are becoming clearer.
Holland & Knight reports that the grid operators submitted tariff proposals in response to FERC’s June orders. PJM’s proposal includes a combined 12-month study process and services that allow power use to be curtailed. The study period is not a guaranteed connection date, and the proposals are not yet approved.
CEQA Developments explains that California’s SB 887, signed in September, requires environmental review for data-center entitlements, including otherwise ministerial approvals, and bars categorical exemptions. A path to faster judicial review is available only to projects meeting demanding conditions; the scope of review remains unsettled.
Smart Water Magazine reports that lawmakers introduced roughly 100 data-center water bills and resolutions across 39 states in 2025–2026. Five states enacted reporting or permitting measures in 2026; Wyoming is considering a cooling-water cap. Most of the measures counted are not established binding laws.
Key Points
- A power connection is increasingly a question of service terms as well as timing: the regional proposals differ on upgrade funding, credit support and whether customers can accept interruptions.
- California’s review requirements add another dimension to the entitlement risk highlighted by recent reporting on local votes that restricted development or reversed approvals. The state law and those local decisions operate differently, but both make the approval route consequential.
Implications
Developers comparing sites should consider environmental review, water requirements and proposed electricity-service conditions together. A favorable power-study process alone would not settle the cost or reliability of service.
If approved, the regional tariffs could place more upgrade costs and operating risk on large customers. Final terms will determine how much that changes individual project economics.
Watchpoints
Watch
FERC decisions and revisions to the proposed tariffs, especially upgrade liability, credit requirements and curtailment terms.
Watch
California guidance or litigation clarifying SB 887’s review scope, mitigation authority and treatment of projects in transition.
Watch
Whether Wyoming advances its draft cooling-water cap, and how enacted state measures are implemented.
Fallout
The clearest updates concern the conditions attached to power access, environmental review and water use—not a new construction milestone.
Power access and project risk
Regional service terms can shape both the cost and reliability of power for a data center.
Fresh developments
Holland & Knight described proposals from six grid operators covering study procedures, upgrade funding, credit support, flexible service and co-located generation. PJM proposed a combined 12-month study pathway and curtailment-based services.
Why we noticed
A shorter or defined study process is not the same as a guaranteed energization date. The financial and operating conditions attached to service may be just as important to a site decision.
Watch for:
- FERC’s treatment of the proposals and any changes to cost allocation or curtailment terms.
California environmental review
SB 887 changes the reported review requirements for data-center entitlements.
Fresh developments
New legal analysis says the law requires CEQA review even for otherwise ministerial approvals and bars categorical exemptions. Judicial streamlining depends on meeting environmental, energy, water and community-benefit conditions.
Why we noticed
Developers cannot assume that an administrative approval avoids environmental review. The law was signed in September, but the review scope and agencies’ mitigation authority remain unresolved.
Watch for:
- Implementation guidance and litigation clarifying review scope and transition treatment.
Water requirements
State water measures vary in substance and legal status.
Fresh developments
Smart Water Magazine, citing the National Conference of State Legislatures, reported roughly 100 bills and resolutions across 39 states in 2025–2026. Five states enacted reporting or permitting measures in 2026.
Why we noticed
The breadth of legislative activity does not amount to a uniform restriction. Project feasibility depends on the requirements adopted in each jurisdiction.
Watch for:
- Wyoming’s draft cap of 0.2 litres of cooling water per kilowatt-hour for qualifying facilities.
- Implementation details for enacted reporting and permitting measures.
Final Thought
The practical question for a site is not simply whether power and approvals are available, but on what terms. Yesterday’s reporting sharpened that question without resolving it.