Applied Digital and Hut 8 are securing long-term leases for large AI data center campuses, with commitments ranging from 210 MW to 704 MW and contract values extending into the billions of dollars. Applied Digital also reported bringing an additional 75 MW online at Polaris Forge 1, while debt financing and high-density cooling systems support the broader buildout. The agreements improve revenue visibility for developers but also increase capital requirements, construction execution demands, and exposure to a small number of large hyperscaler customers.

First Article: 05/21/26

Latest Article: 07/28/26

Summary

  • Applied Digital signed 15-year leases covering 210 MW at Delta Forge 2 and 300 MW of planned capacity at Polaris Forge 3.
  • Applied Digital reported 75 MW of additional operational AI capacity at Polaris Forge 1, bringing the campus to 175 MW live against 400 MW planned under contracts.
  • Hut 8 leased a further 352 MW at Beacon Point, bringing its tenant’s combined campus commitments to 704 MW.
  • Hut 8 also commercialized 245 MW at River Bend under a 15-year Fluidstack lease, with future expansion dependent on additional power.
  • Applied Digital’s reported contracted lease revenue reached about $31 billion and then about $36 billion across different announcements covering four and five campuses, respectively.
  • Applied Digital raised $1.59 billion through senior secured notes and added a $350 million revolving credit facility to support development.
  • Long-duration take-or-pay structures provide revenue visibility, but delivery schedules, debt obligations, and reliance on investment-grade hyperscalers remain important constraints.

History

07/23/2026

The story adds clearer financing and operational detail: Applied Digital not only expanded live capacity at Polaris Forge 1, but also paired the buildout with large debt financing and high-density cooling support. The framing also tightens around the scale of contracted revenue and the dependence on a small set of hyperscaler tenants.

07/22/2026

The story expanded beyond Applied Digital’s lease-driven buildout to include Hut 8 as another major AI campus lessor, while Applied Digital also moved from contracting to execution and financing with live capacity additions and new debt. The emphasis is now more clearly on both revenue visibility and the operational/financial constraints needed to deliver it.

Full History

Featured

Timeline: 69 Days

May 21Jun 4Jun 18Jun 25Jul 9Jul 23

Additional Articles

⭐⭐⭐⭐⭐

Yahoo Finance06-14-2026
Applied Digital announced a 15-year take-or-pay lease for 210 MW at Delta Forge 2 in early June 2026 alongside US$1.59 billion notes and a US$350 million revolving credit facility.
Data Center Dynamics / Dan Swinhoe07-20-2026
Hut 8 announced Beacon Point Phase II commercialization in Nueces County, Texas, with a second 15-year lease covering 352MW of IT capacity and 1GW utility capacity via AEP Texas.
KALB05-26-2026
Governor Jeff Landry announced Delta Forge 1 groundbreaking at England Airpark in Boyce, Louisiana, for a two-building AI data center campus using Cleco power planning and closed-loop water cooling.

⭐⭐⭐

Yahoo / Nauman Khan05-21-2026
Applied Digital secured a long term lease for the Polaris Forge 3 AI campus valued up to 18.2 billion over 15 years, expanding contracted lease pipeline to about 31 billion.
Yahoo06-09-2026
Applied Digital and a U.S. investment-grade hyperscaler agreed on a 15-year, 210 MW take-or-pay lease at Delta Forge 2.
Yahoo Finance / Juby Babu07-27-2026
Applied Digital reported May 31 quarter results driven by hyperscaler AI colocation demand and announced a June 15-year Delta Forge 2 lease.
Yahoo Finance / Laiba Immad05-28-2026
Applied Digital announced a 15-year Polaris Forge 3 AI data center campus lease on May 20, adding about $7.5 billion contracted revenue and lifting backlog to about $31 billion.
Yahoo Finance / Sheryar Siddiq06-02-2026
Applied Digital signed a 15-year take-or-pay 300MW lease at Polaris Forge 3 to expand contracted load and revenue and support further North Dakota campus construction.
The Advocate05-26-2026
Applied Digital plans Delta Forge 1 near Boyce, Louisiana, targeting a summer 2027 opening with 300 MW initial IT load and closed-loop waterless cooling.
Applied Digital06-08-2026
Applied Digital announced a 15-year take-or-pay lease for 210 MW of critical IT load at Delta Forge 2, with initial operations planned for Q1 2028.
PR Newswire07-20-2026
Hut 8 commercialized Beacon Point Phase 2 in Nueces County, Texas, in 2026 by leasing 352 MW of IT capacity under a second 15-year agreement tied to AEP Texas utility delivery.