Last Update: 08/01/2026 at 2:01 PM EST

Avista Data Center Deal Faces Moratoriums

Coverage from The Spokesman-Review, KREM, and others

Articles

10

Active Days

48

The Topic

Avista Data Center Deal Faces Moratoriums topic image

Avista paused negotiations over an unidentified data center project that could draw 125 megawatts beginning in 2029 and expand to 500 megawatts by 2032. The proposal prompted Spokane to adopt a one-year moratorium, while Spokane County considered a nine-month pause, as officials and residents sought clearer protections for power costs, water resources, reliability, noise, and other local impacts. Seattle’s separate one-year moratorium shows similar concerns are spreading to larger Washington jurisdictions.

First Article: 06/09/26

Latest Article: 07/26/26

History

07/23/20260 new articles

The main shift is framing: the Spokane dispute is now presented as part of a broader wave of local policy reactions, with Seattle’s similar moratorium indicating concern is spreading beyond the original jurisdiction. The Avista and Spokane actions themselves are otherwise largely reinforced rather than materially changed.

07/22/20262 new articles

The story has moved from a general pause around a 500-megawatt proposal to concrete local regulatory action, with Spokane now imposing a permit moratorium and Spokane County considering its own. A key new detail is that the load may ramp up gradually from 125 MW in 2029 to 500 MW by 2032, sharpening concerns about when infrastructure and water impacts would hit.

  • Proposed electricity demand could start at 125 MW in 2029.
  • The load could grow to 500 MW by 2032.
  • Spokane adopted a one-year moratorium on data center permit applications.
  • Spokane County proposed a nine-month county permit moratorium.
  • Seattle paused approval of data centers larger than 20 MW.
06/29/20261 new articles

The story has sharpened from a broad pattern of Washington data-center scrutiny into a more specific Spokane-area pause around a proposed 500-megawatt Avista-linked project. The new emphasis is on unresolved site details, water-rights scrutiny, and whether local governments can set standards before the project advances.

  • Avista paused negotiations with an unnamed 500-megawatt data center customer.
  • Spokane City Council considered a one-year moratorium on new data center construction.
  • Mead-area site references appeared in marketing materials.
  • Washington Department of Ecology cited water-rights requirements for well-based supply claims.
  • Spokane Riverkeeper entered the story with water and environmental concerns.
06/21/20263 new articles

The story has broadened from Avista’s paused Spokane negotiation into a wider Washington policy response, with Seattle and Spokane both moving toward temporary restrictions on larger data center development. The main new development is that local governments and utilities are now actively shaping rules around power, water, and infrastructure cost allocation rather than just debating one proposed project.

  • Seattle City Council moved toward a one-year moratorium on larger data centers.
  • Seattle City Light warned about rising load and constrained supply.
  • Water rights proof and permitting are now part of the review process.
  • Avista is slowing negotiations for a 500-megawatt project.
  • Local resistance now includes both utilities and city councils.
06/13/2026Topic Formed

Avista has paused negotiations over a proposed large data center load while it seeks broader policy, regulatory, and community alignment. The dispute has drawn local opposition over electricity demand, water use, infrastructure impacts, and whether new costs would be kept off existing ratepayers. The situation now sits at the intersection of utility planning, municipal regulation, and public scrutiny of hyperscale data center development.