Missouri Data Centers Face Local Pushback
Coverage from WRAL, Columbia Missourian, and others
Articles
31
Active Days
67
The Topic

Google and Amazon Web Services are developing large data center projects near New Florence in Montgomery County, Missouri, while residents challenge the approval process and question effects on water supplies, land use, tax incentives, and electricity infrastructure. Google’s planned $15 billion campus is tied to more than one gigawatt of new generation capacity and a $20 million energy assistance fund, while the nearby AWS project faces a lawsuit alleging violations of Missouri’s Sunshine Law. The developments show how major campuses can advance quickly while communities and local governments negotiate transparency, resource impacts, and who pays for supporting infrastructure.
First Article: 05/20/26
Latest Article: 07/25/26
Summary
- Google is planning a $15 billion data center project, while AWS is developing a nearby campus; the two sites together cover about 1,900 acres.
- Google has contracted with Ameren to add more than one gigawatt of generation capacity and announced a $20 million Energy Impact Fund for nearby households.
- AWS expects to use about 49 million gallons of well water annually at its Missouri project, prompting concerns about aquifer availability and impacts on farms and homes.
- Montgomery County residents have organized through groups including Preserve Montgomery County and Save Montgomery County to seek records, challenge approvals, and oppose the projects.
- A lawsuit alleges county officials violated Missouri Sunshine Law requirements in handling public business and agreements related to the AWS development.
- The projects are linked to tax abatements, road and transmission changes, and broader questions about whether local governments or developers should bear infrastructure costs.
- Richmond County, North Carolina offers a contrasting case in which officials selected a phased Amazon campus after reviewing infrastructure, water capacity, and the company’s record of completing similar projects.
History
The biggest update is that the Google project is now explicitly pegged at $15 billion, and the story has broadened to include a separate North Carolina Amazon campus as a comparison point. The core Missouri dispute remains the same, with transparency, water, power, and infrastructure concerns still driving local resistance.
The story now adds concrete implementation and legal details: Google’s energy and infrastructure commitments are more specific, and AWS is now directly tied to a Sunshine Law lawsuit. The framing also sharpens around public transparency and utility planning rather than just general local opposition.